### WORKS DESCRIPTION

Construction of collector L=41,3 km, dia. from 250-800mm and connections L=9,1 km, with installation of various mechanical equipment.



 

 

 



 

 

### CONTRACT NO: 

KS-SCW-1004-INT-STP-2016-C1-B2

### EMPLOYER:

JKP Vodovod Krusevac

### Employer’s address:

Dusanova 46, 37000 Krusevac, Serbia

### TYPE OF THE PROJECT:

RED FIDIC

### CONTRACT VALUE:

6.604.788,25 EUR

### EXPECTED COMPLETION OF WORKS:

02/2017 - Expected 10/2019 (2 years)



 

 

 

 

 

 





 

 

 

 