### PROJECT DESCRIPTION

Veolia Water Solutions &amp; Technologies is contracted to design and construct an adaptation and improvement of the existing wastewater treatment plant at the Pepsico - Marbo factory in Bački Maglić. The deadline for the execution of the works is 5 months. The scope of work is the preparation of a conceptual solution, procurement, delivery, installation, testing and commissioning of the equipment.

### WORKS DESCRIPTION

Works of Veolia Water Solutions &amp; Technologies d.o.o. Belgrade on the reconstruction and extension of the primary treatment of the existing WWTP Marbo Product d.o.o. includes:

1. Reconstruction and extension of the system for removing sand and solid waste from wastewater.  
     Removal is performed with a combined device through a system of automatic coarse sieves and sandboxes with automatic screening, sand evacuation and automatic removal of dried sand into a container.
2. Installation of screw compactor.
3. Replacement of the existing rotating screen with a suitable system of higher capacity.



 

 

 



   ![](/sites/g/files/dvc2836/files/styles/media/public/image/2022/12/image001.jpg.webp?itok=lVNeAfb2)   





 

 



 

   ![](/sites/g/files/dvc2836/files/styles/media/public/image/2023/08/01._0.jpg.webp?h=77bfd50e&itok=P9Ojv4KK)