PROJECT DESCRIPITON
The distribution pipeline RG 08-02 is conected to the main gas pipeline MG-08 in the Batocina GRC. This pipeline supplies natural gas throughout Western Serbia.
WORKS DESCRIPTION
Procurement and installation of pipeline DN250 mm and DN350 mm for a total length of L=27 Km.
LOCATION:
Batocina, Serbia
INVESTOR:
Public Company "Srbijagas"
CONTRACT VALUE:
5.770.000 EUR
EXPECTED COMPLETION OF WORKS:
12/2011 – 09/2013
![](/sites/g/files/dvc2836/files/styles/default/public/image/2019/08/Izvo%C4%91enje%20radova%20na%20izgradnji%20regionalnog%20gasovoda%20visokog%20pritiska%20RG%20Cvetojevac%20%E2%80%93%20Divostin%2C%20GMRS%20Divostin%20i%20%20GM%20GMRS%20Divostin%20%E2%80%93%20MRS%20FIAT%20Automobili%20Srbija.png?itok=LA_DDFXs)
![](/sites/g/files/dvc2836/files/styles/default/public/image/2019/08/Izvo%C4%91enje%20radova%20na%20izgradnji%20regionalnog%20gasovoda%20visokog%20pritiska%20RG%20Cvetojevac%20%E2%80%93%20Divostin%2C%20GMRS%20Divostin%20i%20%20GM%20GMRS%20Divostin%20%E2%80%93%20MRS%20FIAT%20Automobili%20Srbija%202.png?itok=qmQyEluY)